SaskPower investing $13.5M in Regina's downtown electrical grid

Share

SaskPower says it will be investing $13.5 million in an effort to improve downtown Regina’s electrical grid.

The work will mostly be along 11th Avenue and Saskatchewan Drive between April and August, with work continuing until October on 11th Avenue, a SaskPower news release said.

SaskPower says it will be removing or replacing equipment that has reached or is nearing the end of its life.

Along 11th Avenue, more than four kilometres of cable will be replaced, SaskPower said. New duct banks will also be installed and connected.

Saskatchewan Drive work will include replacing 400 metres of cable and the installation of new duct banks, SaskPower said.

The work means that bus stops will also be relocated along 11th Avenue, with temporary stops being set up.

SaskPower’s vice-president of engineering and construction Ryan Neufeld said the project will mean improved reliability and increased capacity.

“While also allowing our crews to identify and resolve outages quicker, thanks to smart technology,” Neufeld said in the release.

Neufeld also said collaboration with the City of Regina has been ongoing to minimize the effect on downtown traffic.

SaskTel will also be involved in the project.

CTVNews.ca Top Stories

New weight-loss drug Wegovy not a 'magic bullet,' doctor warns

As Wegovy becomes available to Canadians starting Monday, a medical expert is cautioning patients wanting to use the drug to lose weight that no medication is a ''magic bullet,' and the new medication is meant particularly for people who meet certain criteria related to obesity and weight.

Drew Carey is never quitting 'The Price Is Right'

Drew Carey took over as host of 'The Price Is Right' and hopes he’s there for life. 'I'm not going anywhere,' he told 'Entertainment Tonight' of the job he took over from longtime host Bob Barker in 2007.

Stay Connected